We hired a GC for our addition .
And we couldn’t find any GC that would do a firm price .
It was all time and materials .
And I’m so , well I don’t know what to feel.
It took 11 months just to get the damn place just dried in .
One of my neighbors just started an addition and in less than 6 weeks they have Sheetrock hung inside .
They will be finished before me and we started two years sooner .
Took us 18 weeks to get concrete poured after the footings got dug,
There was a six week waiting list for concrete and if it rained on your appointment day and the concrete guys couldn’t pour , you’re back to the bottom of the Six week waiting list .
And that happend three times in a row
Ours was a weird shape , a shallow V shape , had to be that way to fit on the lot .
The roof truss company didn’t want to measure for the trusses until the walls were up since it was a funky shape ,
So thats another six or eight week delay to get the trusses built .
Then a couple days before the roof trusses were being delivered the truss factory caught on fire .
So another six or eight weeks delay .
Then when the trusses were ready again we had to co ordinate the truss install with the crane company , the framers installing the trusses and with Georgia power because the crane company didn’t like the power line and demanded it be dropped while they were using the crane .
Guess what , if it rains on that day , which it did , then you gotta call it off and start all over again with Georgia power and the framers and the crane company to pick a day when they were all available the same day .
We are having to finish the inside and build the deck etc because the Covid lumber prices tripling blew our budget out of the water .
And we couldn’t find any GC that would do a firm price .
It was all time and materials .
And I’m so , well I don’t know what to feel.
It took 11 months just to get the damn place just dried in .
One of my neighbors just started an addition and in less than 6 weeks they have Sheetrock hung inside .
They will be finished before me and we started two years sooner .
Took us 18 weeks to get concrete poured after the footings got dug,
There was a six week waiting list for concrete and if it rained on your appointment day and the concrete guys couldn’t pour , you’re back to the bottom of the Six week waiting list .
And that happend three times in a row
Ours was a weird shape , a shallow V shape , had to be that way to fit on the lot .
The roof truss company didn’t want to measure for the trusses until the walls were up since it was a funky shape ,
So thats another six or eight week delay to get the trusses built .
Then a couple days before the roof trusses were being delivered the truss factory caught on fire .
So another six or eight weeks delay .
Then when the trusses were ready again we had to co ordinate the truss install with the crane company , the framers installing the trusses and with Georgia power because the crane company didn’t like the power line and demanded it be dropped while they were using the crane .
Guess what , if it rains on that day , which it did , then you gotta call it off and start all over again with Georgia power and the framers and the crane company to pick a day when they were all available the same day .
We are having to finish the inside and build the deck etc because the Covid lumber prices tripling blew our budget out of the water .